Demand Side: AI Is Blowing Up the Power Meter — Asia’s Power Bill, Part I
By Jiuri in Tokyo
Start with one number.
According to the International Energy Agency, a typical AI data center can consume as much electricity in a year as the residential power use of a small or medium-sized city.
TrendForce offers an even more direct measure. Global data-center power demand capacity is expected to reach 161 GW in 2026, up 31% year on year. AI servers will account for 33.4% of that demand, compared with less than 25% in 2025.
In other words, the surge in data-center electricity use is not simply because more data centers are being built.
It is because far more power-hungry equipment is being packed into the same amount of space.
A traditional data-center rack typically draws around 2.5 kW.
In the AI era, racks exceeding 30 kW are already common, while systems are rapidly moving toward 120 kW and 240 kW per rack.
NVIDIA’s next-generation Kyber NVL144 rack-scale system is targeting roughly 600 kW per rack.
One AI rack can consume as much electricity as dozens of households.
The IEA expects global data-center electricity consumption to reach 945 TWh by 2030, almost equivalent to Japan’s annual electricity use.
AI’s share of that consumption is expected to rise sharply, reaching roughly 35% to 50%.
No one can say exactly how many data centers are currently being built across Asia.
But one thing is increasingly clear:
AI is pushing the power meter toward its limits.
South Korea: 15 GW of Demand, 1.9 GW of Local Supply
Consider Yongin, South Korea.
The area is being developed into one of the world’s largest semiconductor and AI data-center clusters.
At full operation, it could require 15 to 16 GW of electricity — roughly equivalent to one-quarter of total power demand in the Seoul metropolitan area.
But Yongin’s current local supply capacity is only around 1.9 GW.
That is a gap of more than eight times.
Korea Electric Power Corporation is developing a 1,153-kilometer transmission network, with completion targeted for 2036.
Whether it can be finished on schedule remains uncertain even according to project assessments.
By early 2026, political voices had already begun calling for parts of the cluster to be relocated to regions where electricity is more readily available.
Wood Mackenzie’s assessment of an AI cluster in South Korea’s Honam region is similarly concerning.
At full operation, regional peak demand could rise from 11.8 GW to 19.1 GW, while effective generation capacity under current plans would reach only 16.8 GW by 2030.
That leaves a shortfall of around 2.3 GW.
South Korea’s dilemma is a microcosm of the wider Asian problem.
AI electricity demand is rising quarter by quarter.
Power infrastructure is still being planned on a decade-long timetable.
Japan: Grid Margins So Thin That “Emergency Auctions” Are Needed
Japan’s data-center electricity demand is expected to increase from around 0.64 GW in 2026 to 6.61 GW by 2035 — a tenfold increase in less than a decade.
Eight major Japanese utilities, including Tokyo Electric Power Company, plan to construct around 30 new substations by the early 2030s, adding roughly 15 GW of capacity.
That is equivalent to the output of around 15 nuclear generating units.
But Japan’s problem is not simply total capacity.
It is timing.
In August 2026, under a scenario combining extreme heat with prolonged power-plant outages, the reserve margin in the Tokyo area was at one point projected to fall to as low as 0.9%.
In response, the Japanese government proposed a 12 GW capacity auction for the Tokyo region to secure available generation in advance.
One of the world’s most developed urban economies now needs special capacity procurement to make sure electricity remains available during peak summer demand.
Southeast Asia: Racks Are Being Sold Faster Than Power Can Arrive
In Johor, Malaysia, operating IT capacity reached 1,110 MW by the first half of 2026.
Another 602 MW was under construction, while 2,486 MW was planned.
But analysts cited by Xinhua have identified electricity availability as the primary constraint, while water sustainability is becoming an increasingly important factor in project approvals.
Johor state data show that among 65 approved data-center projects, 21 are already operating and are expected to consume nearly 1.1 GW of power.
Projects under construction and in planning could require another 4 to 5 GW.
Johor aims to add around 5 GW of solar generation capacity by 2030 or 2031 to help meet that demand.
But 5 GW of solar capacity is not the same as 5 GW of reliable power.
Solar is intermittent.
Data centers require stable electricity 24 hours a day, seven days a week.
Singapore faces even tighter constraints.
Peak electricity demand is expected to rise from 8.2 GW in 2025 to 11.9 GW by 2032, with semiconductor production and data centers among the main drivers.
Singapore imposed a moratorium on new data centers between 2019 and 2022.
Since then, it has controlled new capacity through a Data Centre Call for Application process.
The latest round requires applicants to source at least 50% of their electricity from green energy.
A city-state is effectively using administrative controls to ration access to electricity for computing infrastructure.
How Can the Gap Be Filled?
TrendForce estimates that global data-center power demand could reach 490.7 GW by 2030.
Yet under existing grid capacity and currently planned generation, only around 222.6 GW may be available.
That leaves a shortfall of roughly 268 GW.
What does 268 GW mean?
It is roughly equivalent to the installed capacity of more than 200 large nuclear power units.
And that gap cannot be closed simply by building more power plants.
Electricity has to travel from the generating station through substations, transmission lines and distribution networks before it reaches the power modules inside a server rack.
Every link in that chain has its own construction timetable, approval process and physical limits.
The demand side has already put the numbers on the table.
The supply side has fallen far behind.