Computing Has the “Ticket,” but the Grid Cannot Afford the “Platform”
APEC and the Changing Global Economy, Part II
By Li Da in Tokyo
Artificial intelligence was an unavoidable topic at APEC in Shenzhen. The Shenzhen Initiative called for a responsible AI governance framework that would allow AI to develop faster and benefit more people.
But several thousand kilometers away in Yongin, South Korea, reality is posing a different question: the factories are already under construction and equipment will soon begin arriving — but where will the electricity come from?
Yongin is building a massive semiconductor cluster in which Samsung and SK hynix have committed heavily. Once fully operational, the complex is expected to require 15 to 16 GW of electricity, close to one-quarter of the total power consumption of the Seoul metropolitan area. Current local supply capacity, however, is only around 1.9 GW. The additional electricity will have to be supplied gradually through new generation capacity and cross-regional transmission networks. Korea Electric Power Corporation once proposed that the two companies prepay five years of future electricity bills to help finance grid construction in advance. After calculating the cost, the companies declined.
On one side are computing investments worth tens or even hundreds of billions of dollars. On the other are transmission networks that can take five to eight years to build. The capital clock of AI expansion is colliding with the physical limits of power-grid construction.
Computing Power Has Developed a Much Bigger “Appetite”
In the past, data centers were primarily used for data storage and conventional computing. With the rise of generative AI and large language models, training and inference require growing numbers of high-performance chips, pushing electricity demand at data centers sharply higher.
How many servers a data center can accommodate increasingly depends on how much electricity it can secure.
AI training and inference require large numbers of high-performance chips. The denser the servers, the greater the power demand of each rack. A traditional data-center rack typically requires only a few kilowatts, while AI server racks commonly consume tens of kilowatts, with some high-density systems requiring even more. Electricity is no longer simply an operating expense. It has become a hard constraint determining whether a computing project can be built at all — and whether it can expand.
Yongin is not an isolated case. In Osaka, Japan, NTT DATA is in discussions with U.S. AI company Anthropic over the construction of a large data center with planned maximum power intake of 500 MW. But information released by Osaka Prefecture in October showed that the relevant bay-area grid has almost no spare capacity. Strengthening the network sufficiently to accommodate such a large load is expected to take around eight years. The project developers are therefore also considering options such as on-site generation and fuel cells.
Johor, Malaysia, presents another version of the same problem. Driven partly by spillover demand from Singapore, its operating data-center capacity surged from 94 MW in 2023 to 1,110 MW in the first half of 2026, with another roughly 3,088 MW under construction or planned. The vacancy rate for colocation data centers is only 0.7%, meaning demand is so strong that almost no space remains available. But however strong that demand may be, electricity, land and water all have to be aligned on the same timetable.
Two Timetables That Do Not Match
The central contradiction is not necessarily an absolute shortage of electricity. It is that the construction cycles of computing infrastructure and power infrastructure operate on completely different scales.
Data centers move according to a market-driven timetable: chips are upgraded on an annual cycle, AI models evolve over a matter of months, and data-center projects are pushed forward as quickly as possible. Power grids operate on a different clock. New generating capacity, substations and transmission lines require planning approvals, environmental assessments, land acquisition and engineering work, often taking several years or longer.
Yongin is a typical example. The electricity required by the cluster not only has to be generated; it also has to be delivered to the site through transmission networks. The South Korean government and power companies have already drawn up phased supply schedules, but transmission lines have their own construction timelines. Companies can adjust equipment procurement plans, but they cannot make an unfinished transmission line deliver electricity ahead of schedule.
ADB President Masato Kanda has repeatedly been quoted as saying that capital itself is not the main constraint; the key is having projects that are investment-ready and capable of being implemented. In other words, money may be available, but the ability to prepare, approve and construct projects determines whether that capital can actually become infrastructure. Demand for computing power is exploding quarter by quarter, while grid delivery is planned on a decade-long horizon. That timing gap is becoming a hidden cost that the expansion of the digital economy must increasingly bear.
How Much Can APEC’s “Table” Really Do?
That brings the discussion back to APEC in Shenzhen.
At the APEC Energy Ministers’ Meeting in September 2026, members adopted the APEC Policy Recommendations on the Two-Way Empowerment of Artificial Intelligence and Energy (2026–2030) and established a new “AI + Energy” task force under the APEC Energy Working Group. It is the first policy recommendation document within the APEC framework specifically focused on the mutually reinforcing relationship between AI and energy.
The document calls on member economies to strengthen coordinated planning between computing infrastructure and energy infrastructure, so that data-center development and electricity-supply arrangements can be better aligned. It also encourages the use of AI to improve forecasting, dispatch and operational efficiency in power systems.
This means the relationship between AI and energy is no longer simply one between a major electricity consumer and a power supplier. AI requires electricity, but power systems can also use AI to operate more efficiently.
What APEC can do, however, is promote policy dialogue, technical cooperation and the sharing of experience. It cannot approve a national grid project on behalf of a member economy, nor can it make an unfinished transmission line start delivering electricity early.
APEC in Shenzhen is discussing how AI should develop. Yongin and Osaka remind us that the expansion of computing power still has to pass through the electricity bottleneck.
Computing power can accelerate, but the grid has its own construction schedule. The economies that can bring these two clocks as closely into sync as possible will be better positioned in the next round of AI competition.