Supply Side: Power Grids Are Racing to Catch Up, but Computing Demand Is Pulling Away — Asia’s Power Bill, Part 2
By Li Da in Tokyo
The previous installment examined the demand side: AI is pushing electricity use to the limit. This time, the focus is supply. The conclusion is straightforward. Power grids are racing to catch up, but they cannot match the speed of growth in computing demand.
Thailand’s Eastern Economic Corridor has a planned data-center pipeline of 2.87 GW, concentrated in Chonburi, Rayong and Chachoengsao. Local substations are already close to saturation. A World Economic Forum analysis published in November 2026 put the problem plainly: facilities requiring more than 50 MW face grid-connection waits of over 18 months.
Thailand does not lack generating capacity. Its reserve margin exceeds 25 percent. The problem is getting that electricity into the Eastern Economic Corridor. The Thailand Board of Investment received applications for 36 data-center projects in 2025. A draft plan for 2026–2050 projects data-center power demand of 8,611 MW by 2050. Generation is sufficient; transmission and distribution are not.
That is the supply-side reality. What Asia lacks is not power stations, but the wires needed to deliver electricity to the server rack.
Johor’s 30 Percent and the Missing Link
Johor, Malaysia, is one of the region’s most concentrated data-center markets. Industry estimates put utilization of the state’s overall grid at only about 30 percent, suggesting at first glance that ample headroom remains.
Demand, however, is highly concentrated. Local substations and connection lines serving the Sedenak and Nusajaya technology parks are already under strain. BMI, a Fitch Solutions company, forecasts that Johor’s data centers will require about 30 TWh a year by 2031, equal to 18 percent of electricity supplied across Peninsular Malaysia, up from 6 percent in 2026. That would absorb more than 90 percent of the peninsula’s projected net increase in generation over the same period.
Geography makes matters worse. The peninsula’s grid is not connected to Sarawak, where most of Malaysia’s growth in hydropower is located. Peninsular Malaysia must therefore rely on natural gas to cover the shortfall. BMI expects thermal generation capacity to rise by a net 3 GW between 2029 and 2031, while warning that “some retirement plans may be delayed given tight supply margins.”
Grid companies are trying to close the gap. Tenaga Nasional Berhad, Malaysia’s national utility, plans to invest 43 billion ringgit in grid upgrades. But BMI adds a crucial caveat: “Large grid projects typically take five to ten years to complete.”
Five to ten years. A data center can move from contract signing to operation in two to three. That is the timing mismatch at the heart of the problem.
Bangkok’s Deposit: A Ticket to the Connection Queue
Thailand has introduced a new tool: a deposit.
In May 2026, the Energy Regulatory Commission introduced the Power Commitment Guarantee, or PCG. Data-center developers reserving large blocks of grid capacity must provide a financial guarantee of 4.5 million baht per MW. A 50 MW project must post about 225 million baht, while a 100 MW project must provide roughly 450 million baht.
The objective is not to raise money, but to screen out speculative projects that reserve capacity without building. The Board of Investment received 36 data-center applications, yet few have moved ahead. Grid capacity is booked, construction does not begin, and developers that genuinely intend to build are left waiting. The deposit acts as a filter.
For a hyperscale operator, 450 million baht for a 100 MW facility is not prohibitive. But the signal is clear: grid access is no longer a free, first-come-first-served resource. It is a place in line that now requires a down payment.
The ASEAN Power Grid: Signed, but Electricity Has Yet to Cross
Cross-border transmission is widely seen as part of the solution: generate power where resources are abundant and deliver it where demand is strongest.
In November 2026, all ASEAN member states completed the signing of the Enhanced Memorandum of Understanding on the ASEAN Power Grid. The Philippine Department of Energy called it “a significant milestone in regional energy cooperation.” The memorandum covers infrastructure planning, institutional arrangements, policy and regulatory development, and financing, including onshore transmission lines and subsea cables. Electricity-market integration will proceed on a “voluntary and progressive” basis while respecting national autonomy.
The language is cautious, and the pace is unlikely to be fast. As recently as April 2026, the ASEAN Centre for Energy was still defining the mandates of three working groups covering policy, regulation and technology. The long-running Laos–Thailand–Malaysia–Singapore Power Integration Project currently trades 200 MW, roughly enough for one medium-sized data center.
The vision is to achieve a fully integrated ASEAN power grid by 2045. Data centers cannot wait that long.
ADB’s Ledger: Capital Is Available, Bankable Grid Projects Are Not
An Asian Development Bank report released in November estimates that Southeast Asia will need $7.1 trillion in infrastructure investment through 2040, including $3.6 trillion for power and $584 billion for digital infrastructure. Public investment can cover only 45 percent, leaving an annual gap of $264 billion.
Yet a remark by ADB President Masato Kanda at the ASEAN Business and Investment Summit was even more telling: “Capital is not the constraint. Investable projects are.”
In other words, the money is available, but too few grid projects are ready to break ground. ADB identifies three requirements: predictable rules, transparent procurement and more project preparation. Each takes longer than simply committing more capital.
Supply Cannot Keep Pace with Demand
The outcome is increasingly clear: computing demand that expands quarter by quarter cannot wait for power grids built on decade-long timelines.
In theory, an AI data center takes two to three years to build, while a grid upgrade takes five to ten. Negotiations over cross-border power rules proceed on a “voluntary and progressive” basis, and the ASEAN Power Grid is targeting 2045.
In practice, South Korea’s Yongin cluster will require 15–16 GW, but local supply capacity is only 1.9 GW. The transmission network is scheduled for completion in 2036, and the report itself acknowledges uncertainty. Johor’s data centers are expected to consume 18 percent of Peninsular Malaysia’s electricity by 2031, while TNB’s grid upgrades will take five to ten years. In Thailand’s Eastern Economic Corridor, grid connections already involve an 18-month queue, and the deposit system has only just begun.
Demand is multiplying on a quarterly timetable while supply is planned by the decade. The gap cannot be closed simply by building a few more power plants. Electricity must travel from generators through substations, transmission lines and distribution networks before reaching a rack’s power module. Every link has its own construction schedule, approvals and physical limits.
The grid is running. Computing demand is already far ahead.
The next chapter turns to an external shock: how difficulties in the Strait of Hormuz could travel all the way to Asia’s electricity meters.